Sample, made-up job
Draft · 1 line needs a look
Sent to the GC after the office approves
- Job
- 2417 · Clinic TI, Meridian
- GC
- Sample GC Co.
- Foreman
- M. Ortiz
- Crew / hours
- 4 · 32.0 h
Crew and hours
- Sheet metal crew of 4, 8.0 h each 32.0 h
Work completed
- 3rd floor supply duct, 24x12, gridlines C to F D-310140 / 220 LF64%
- Hung VAV boxes 3-04 and 3-05 D-3402 / 9 EA22%
Delays
- Ceiling grid on 3 not released by GC. Crew on standby. 2.0 h
- Fittings from our supplier arrived lateInternal 0.5 h
Extra work
- Moved 2 supply diffusers in 3-07, directed by GC super “Jay” 3.0 h Needs a look“Jay” isn’t on the contact list.
Safety
- Toolbox talk on ladder safety. No incidents.
Tomorrow
- Planned: finish 3rd floor supply duct to gridline H
Internal notes
- Need 6 more 24x12 hanger kits before Thursday